This declassification project included an interior demolition of Class 100 clean room space in 3 buildings simultaneously totaling 70,000 sq. ft.
Involved the decommissioning and removal of numerous process piping, toxic gas systems, HVAC systems (flammable, scrubbed, and general exhausts), electrical panels and feeders, interior clean room and sheetrock wall systems, fire sprinkler and fire alarm systems.
All activity was done concurrently with the remainder of the building occupied and functional.